Next Saturday, 6/7/08, will be the 4th Saturday for the conversion of Electric Bug. Thanks to all who have helped so far! George, Matt K., Jim D., Matt R., Steve Clarke, and Wayne (please forgive me if I've forgotten anyone).
We've achieved so much - the engine and trans are mounted, and we're ready to continue.
Next Saturday we will be installing the front battery box with a new mount fabrication, tack-welding the main battery box to the frame of the vehicle, and start the installation of the flex tubing underneath the car for the 2/0 cables. I've also ordered most of the main components and should have those shipped within a week or two.
So come on down to 2823 S. Highland in Berwyn, IL. As always, I'll provide coffee, donuts, and juice. We begin at 9am and usually go until noon or 1pm.
All are welcome, so come on by to see how an EV is built!
-Todd