The wall is insulated and the first sub-panel, and 50 amp outlet box are mounted and have conduit to them. With the help of my DAUGHTER! we pulled the worst of the first run, the 30 or so feet from the main to the first pull through corner. This has 135 degrees of bends in it, the rest have less. Hopefully tomorrow I can get the pull complete to the subpanel and start connecting things.
Then it would be time to start on the second sub panel. (which has conduit most of the way already)
I am definitely going to have to lube those more complex runs for the garage, it was all we could do to move through 135 degrees of bend, and this run was a much lower fill ratio than the garage will be.
Progress continues.